Robert Niggebrugge CofC CSCI 362 Fall 2020 Blog

HW19: Chapter 23



23.6) Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized